All posts by Practical Law Construction

REUTERS |

I read with interest Paul Bury’s blog, which touched on the case of Zagora Management Ltd v Zurich Insurance plc as it relates to claims against approved inspectors. I’m interested in the case for a different reason: it’s one of the first superior court decisions, post-Grenfell, that deals with the liability consequences of high-rise properties containing combustible cladding.

As is now etched in our collective memory, on 14 June 2017, a fire broke out in Grenfell Tower, in West London, resulting in the tragic loss of life. Since the time of this event, many owners of high-rise buildings across the UK have learned that their cladding contains combustible components, which may include aluminium composite panels with combustible cores (ACPs), phenolic insulation, or a wide range of other components – or is missing cavity barriers or other fire protection measures.

A challenging question that owners and contractors may ask their legal advisors is the extent to which the (potentially very substantial) cost of removing and replacing the combustible components, or rectifying these other issues, can be recovered. Since Grenfell, claims of this nature have been (and are being) made against a variety of participants including contractors, subcontractors, consultants, approved inspectors and insurers. Continue reading

REUTERS |

The Court of Appeal’s judgment in S&T v Grove is still the most talked about construction case almost four months after it was handed down, which has much to do with the questions that parties and representatives raised about its practical implications. I discussed some of these implications shortly after the judgment was handed-down, and in particular the Court of Appeal’s finding that:

“… both the Act and the contract must be construed as prohibiting the employer from embarking upon an adjudication to obtain a re-valuation of the work before he has complied with his immediate payment obligation.”

I said at the time that:

“… it is quite clear that, despite section 108 providing a party with the right to refer a dispute to adjudication ‘at any time’, the Court of Appeal has found that there is a fetter on this right, namely that where an employer has not paid the notified sum in accordance with section 111, that employer is unable to refer a dispute concerning the correct value of the works to adjudication.”

In M Davenport Builders v Colin and Julia Greer, Stuart-Smith J has applied S&T v Grove, but with a twist that arguably dispels the conclusion that there is a fetter to the right to adjudicate. Continue reading

REUTERS | Thomas Peter

Construction and engineering contracts often contain provisions specifying that, within a particular time, one party (traditionally the contractor) must notify the other (the employer and/or the contract administrator) of a claim or the likelihood that it might advance a claim. Sometimes these “time-bar” notice provisions are elevated beyond being merely an obligation, to the status of a condition precedent to being able to pursue a successful claim. If such provisions are enforceable, they can be severe: a failure to serve the required notice in the required timescale will be fatal, regardless of the merits of the underlying claim. A well-known example of such a provision is found in clause 20.1 of the 1999 FIDIC contracts.

Unsurprisingly, many contractors have found themselves needing to construct nuanced arguments to get around the “trap” of clause 20.1. As the default final dispute resolution mechanism in FIDIC contracts is arbitration, reported court decisions giving guidance on the specific language used are rare, although some (but most definitely not all) other widely-used standard forms contain similar provisions. There are, nonetheless, a stock of standard arguments that are typically deployed.  Continue reading

REUTERS | David Gray

With the Court of Appeal’s decision in Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd just a few weeks old, it is hardly surprising that people are looking again at the relationship between insolvency law and adjudication, noting that in cases of liquidation where parties have a cross claim, construction law defers to insolvency law.

This was clearly illustrated in Gregg Nowak Ltd v CSS Electrical Distributors Ltd, which came before HHJ Bailey earlier this month. Continue reading

REUTERS | Wolfgang Rattay

The slip rule is an essential part of the adjudicator’s toolbox, for situations when a mistake has crept into our decision or, as I put it back in 2011:

“It is a handy implied term for those occasions when adjudicators make a mistake.”

It took on statutory form in 2011 with section 108(3A) of the Construction Act 1996 and paragraph 22A of the Scheme for Construction Contracts 1998. Prior to this, we relied on a number of cases, including Bloor v Bowmer & KirklandO’Donnell Developments Ltd v Build Ability Ltd (where Ramsey J said the adjudicator must not be “giving effect to second thoughts or intentions but of giving proper effect to his first thoughts”), Redwing Construction Ltd v Wishart and YCMS Ltd v Grabiner (where Akenhead J said that the adjudicator’s mistake must be a “genuine slip which failed to give effect to his first thoughts”).

Over the years, I have looked at the slip rule a few times, most recently to consider Lady Wolff’s judgment in NKT Cables A/S v SP Power Systems Ltd, where she confirmed that it is there to enable an adjudicator to correct clerical or typographical errors, not to allow “changes to the reasoned or intended basis of the decision”.

I’m looking at it again today because, in Axis v Multiplex, Roger ter Haar QC held that, when used properly, the slip rule extends to consequential corrections.  Continue reading

REUTERS |

The extent to which property owners of a defective building have a valid claim against professionals with involvement in the development is a subject that has recently seen an upsurge in interest and litigation. In the past months two TCC judgments have been published that consider the particular role and potential liabilities of approved inspectors (AIs): Zagora Management Ltd and others v Zurich Insurance plc and others and Lessees and Management Company of Herons Court v Heronslea Ltd and others.

To the disappointment of property owners, and perhaps the relief of insurers, these cases demonstrate the difficulties claimants face in succeeding against AIs.  Continue reading

REUTERS | Gilles Adt

Summer 2018 will be remembered as a special time by many readers of this blog: whether it was the spectacular weather, the giddy heights hit by the England football team, or Fraser J’s decision in Michael J Lonsdale (Electrical) Ltd v Bresco Electrical Services Ltd (In Liquidation), it was a summer to remember.

To recap on the latter, Fraser J granted an injunction preventing an insolvent contractor from pursuing an adjudication. The case was the subject of a considerable amount of commentary, including from my colleague Marcus Birch. Importantly, Bresco was in liquidation, rather than some other insolvency procedure. The case was seen as the death knell for the practice of liquidators bringing adjudications.

Perhaps understandably the decision of HHJ Waksman QC in Cannon Corporate Ltd v Primus Build Ltd received considerably less attention. In that case, the judge granted summary judgment and refused a stay of execution to an insolvent contractor in a company voluntary arrangement (CVA). In other words, a company in a CVA might (depending on the facts) still be able to refer matters to adjudication.

In a conjoined appeal, the Court of Appeal has upheld both decisions, and in doing so has provided some useful guidance on whether adjudication remains an option for insolvent companies. Continue reading

REUTERS | Max Rossi

It was only published at the end of last week, so I’m not sure if you’ve had chance to look at Coulson LJ’s judgment in Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd, Cannon Corporate Ltd v Primus Build Ltd.

If not, then you should. It contains some important stuff about liquidation and CVAs, and when it is appropriate (and possible) to adjudicate if the referring party is subject to one of those processes. I’m hardly giving the game away to say that you can’t if the party is in liquidation, but you can if it is subject to a CVA. As ever, it is a bit more complicated than that because, although Coulson LJ decided that the adjudicator has jurisdiction in both cases (to borrow Mr Crangle’s phraseology), it will be “an exercise in futility” if the referring party is in liquidation. This was described as theoretical jurisdiction and led Coulson LJ to conclude that adjudication and the insolvency regimes are incompatible. In his view, the solution to that incompatibility is for a court to grant an injunction to prevent an adjudication from continuing and to prevent the liquidator and, more importantly, the responding party from wasting costs.

It is all very interesting and I’m sure we will see plenty of column inches devoted to these aspects of the judgment. However, I think the waiver points applicable to jurisdictional reservations that are discussed in the Cannon v Primus part of the judgment are of greatest use to parties and those representatives who deal with adjudications on a day to day basis. After all, how often do adjudications involve insolvent parties? I certainly haven’t dealt with one for some time now. By contrast, I see general (and specific) reservations all the time. Therefore, waiver is what I plan to focus on today. Continue reading

REUTERS |

Many a construction dispute turns on defects. A significant subset of those turn on whether the existence of defects prevents practical completion from taking place. It’s not surprising that these situations are contentious: contractors are keen that practical completion is certified so as to avoid or limit their liability for liquidated damages, trigger the return of retention monies and, often, to bring about an assessment of sums they consider due under the final account. Employers may be understandably reluctant to take possession of a property which they consider defective and by resisting practical completion an employer can put pressure on a contractor by withholding sums that would otherwise become due.

Practical completion is therefore an important concept in construction contracts, although one that is often not precisely defined, which can cause uncertainty and hinder the operation of the contract. Continue reading

REUTERS | Ricardo Moraes

Football’s transfer window is open and the papers are full of stories about who may be leaving, who may be arriving and who hasn’t got any money to spend. Speculation is rife, but does anyone wonder what really happens behind the scenes when a footballer’s contract of employment is terminated and he goes off to play for another club?

Apparently, there are rules about this. In England, the FA is the governing body and it has rules that all clubs and players are bound by. These rules extend to termination, either “with just cause” or ” with a sporting cause” and also encompass the “consequences of terminating a contract without just cause”.  Essentially, it means compensation is payable by the party in breach (usually the player). If the player has to pay compensation, he is jointly and severally liable with his new club to pay the old club. In practice, I guess the player’s transfer fee is the “compensation”.

This is all set out in some detail in the judgment in Fleetwood Wanderers Ltd v AFC Fylde Ltd, where the Commercial Court had to decide whether an arbitrator had breached his section 33 duty to act fairly and impartially. Continue reading

Share this post on: