Liquidated damages (LD) clauses are a fixture of construction contracts. As we all know, they are a secondary obligations to pay an agreed sum of money, arising upon breach of a primary obligation of the contract. In the case of a construction contract, this will invariably be in the event of delay: the failure to complete the works by a specified date.
LD clauses are the paradigm of something agreed very much in the hope that it will never be needed, when in the rosy glow of the start of a project, everyone is confident it will be completed on time. As a consequence, it may be that parties negotiating the sum don’t necessarily give it as much thought as they later feel it deserves when a project is overrunning, and the LDs are racking up.
However, the recent judgment of Mr Richard Salter QC in GPP Big Field LLP and another v Solar EPC Solutions SL (formerly known as Prosolia Siglio XXI) has confirmed, following on from Makdessi v Cavendish Square, that a genuine pre-estimate of loss does not need to be negotiated in minute (or indeed any particular) detail in order to avoid being seen as an unenforceable penalty. Continue reading