Monthly Archives: September 2015

REUTERS | Carlo Allegri

Claims versus variations

An instructed variation is not the only way a contractor’s work under a project can be altered. Equally it is not the only contractual ground for the contractor to claim additional compensation. Construction contracts will normally also contain provisions allowing the contractor to make “claims”. For example, the site conditions may be different to those contemplated, such as unexpectedly bad ground conditions or restrictions on site access. Alternatively, the employer may fail to fulfil its obligations, such as providing design information or approvals late.

In each of these situations an event (or a discovery relating to the site) that is the employer’s risk under the contract, may result in the contractor undertaking the works in a different way as well as increasing its costs. Such events will typically give rise to a right to extra money (and possibly time) either under a particular clause of the contract or under a general claims provision, such as a loss and expense clause.

A comparison between variations and claims is interesting for a number of reasons, not least because of the possibility that the contractor may have a right, in certain circumstances, to choose which provision it relies upon to claim additional compensation. Continue reading

REUTERS | Hannibal Hanschke

When I first started writing about experts, I wasn’t aware of how frequently the topic pops up in judgments, or the sort of issues that arise. Now it seems hardly a week goes by without a judge commenting on an expert’s good, or more often, bad behaviour or whether there is a need for an expert in a particular case.

We are all familiar with the fact that construction litigation (big or small) relies heavily on experts. While few of the cases I’ve been reading recently actually concerned construction disputes, the underlying principles affect us all. Therefore, I was interested to see a Chancery judge’s guidance in British Airways plc v Spencer and others on the principles for deciding whether expert evidence is necessary. Continue reading

REUTERS | Shutterstock

Although alliance contracting has been used in the UK over the past 15 years, it has never quite won the affections of contracting parties here which has been achieved in other jurisdictions.  However, recent trends suggest that the move towards alliance contracting is gaining momentum. Network Rail has already moved to the alliance model for major infrastructure works and the Department of Health has used the alliance model for a major IT and services outsourcing project for the NHS. Continue reading

REUTERS | Anindito Mukherjee

Well, in the words of Bananarama, it’s been a cruel cruel summer: well, at least August has. The weather has been shocking in the UK and I’ve heard more than one person say that they’ve already put their central heating on. Not only that, Matt and I have only had one TCC case to write about. Consequently, this week I thought I would look further afield, and specifically to Hong Kong.

Earlier in the summer, the Government of Hong Kong published a consultation on the introduction of Security of Payment legislation (SOPL) in the region, including statutory adjudication. I’ve been lucky enough to be invited to Hong Kong later this year to talk to prospective adjudicators on decision writing, so I’ve looked at the consultation in some detail. Continue reading

Share this post on: