REUTERS | Mike Blake

Whose plant is it anyway?

When things go wrong on a project we tend to think that the contract will finally determine issues between the parties. Of course, this is not always the case: we must not forget about statutory rights.


Common contract terms

A standard term in many building  contracts allows the employer, having determined the employment of its insolvent contractor, to use that contractor’s plant, machinery and materials to complete the works. This gives the employer some comfort that it can get on with the job if its contractor goes bust, without having to incur time and money in procuring these items afresh.

The Insolvency Act

So that’s clear cut, isn’t it? The insolvency practitioner will simply have to wait until the works are complete before getting his hands on any remaining plant, machinery and equipment.

Possibly not.

This is because this type of clause appears to frustrate the statutory duties and powers given to an insolvency practitioner, particularly section 234 of the Insolvency Act 1986. Section 234 gives the insolvency practitioner the power to go to court to require the employer to deliver up any of the insolvent company’s property so the assets can be realised as soon as possible. It does not contemplate extending the liquidation for some indeterminate period whilst the employer completes the project.

The case law

In Smith (administrator of Cosslett (Contractors) Ltd) v Bridgend County Borough Council [2001] UKHL 58 (8th November, 2001) the House of Lords held that the contractual right of the employer to sell the insolvent contractor’s assets and apply the proceeds towards settling the employer’s claims against the contractor, amounted to a floating charge over the assets of the contractor, which was void as against the administrator (in that case) as it had not been registered. The House of Lords also held that the administrator had the power under section 234 to recover assets belonging to the contractor and a claim for conversion against the employer for selling the contractor’s assets.

The House of Lords judgment in Cosslett did not consider how section 234 operated where the employer had a contractual right to use (but not sell or dispose of) the contractor’s plant once the insolvency had occurred. However there must be the same risk that the courts would uphold the insolvency practitioner’s powers to get his hands on the assets under the Insolvency Act in these circumstances, even if they are at odds with the terms of the contract.

The reality

In our experience, parties who find themselves in this situation, including insolvency practitioners, tend to try and work through the problems rather than strictly enforcing their contractual or statutory rights. However, with the number of insolvencies that are currently affecting the industry we would be interested to hear whether anyone has had to grapple with this issue.

2 thoughts on “Whose plant is it anyway?

  1. As an Employer, we have recently had to deal with this issue. The contract in question was a civils package on an ICE 7th (Bridgend was 5th I think). On the Contractor’s insolvency, we initially asserted our contractual rights against the various finance companies, hirers and material suppliers queuing up at the gates. We duly recieved letters from the finance companies citing Bridgend and accompanying threats to sue for conversion if we asserted our contractual rights.

    We discovered the following practical issues:

    a) competent replacement contractors (including subbies whose contracts are taken over) are not prepared to use an insolvent main contractor’s plant (there are a plethora of safety and insurance issues);

    b) even if a contractor is prepared to use plant, these will need to be free-issued and hence the Employer assumes the responsibility;

    c) it does not go down well with the supply chain (which you are likely to need to finish the job) if you try and withhold materials and plant which have been delivered to site and which the Employer has not paid for when your only reason for doing so is a main contract which states you are entitled to use them regardless. This, unsuprisingly, cuts little sway with unpaid scaffolders.

    d) if you do use the equipment and then try and sell it, the title issues mean that the proceeds are unlikely to be worth the hassle.

    e) overall, it is generally a lot of hassle in which no-one is a winner and simply acts as distraction to getting a replacement contractor on to complete the works.

    Where a contractor owns all of its own plant, free of finance, you may want to register the floating charge. Back on planet Earth, if the contractor goes under, the lesson learnt is to keep what you have paid for and to which you have good title – let the rest go, and concentrate on getting a replacement contractor in.

Comments are closed.

Share this post on: