REUTERS | Kai Pfaffenbach

The last time I looked at the dispute between Rawlings Consulting (UK) Ltd and Maelor Foods Ltd, I was talking about HHJ Eyre’s judgment and how the arbitration clause in a JCT standard building contract can “trump” a Part 8 application for declaratory relief.

This time, I’m looking at HHJ Stephen Davies’ judgment and Maelor’s (the employer) jurisdictional challenge, based on the argument that the dispute which Rawlings (the contractor) referred to adjudication arose under more than one contract.  Continue reading

REUTERS |

Last year, a developer client raised concerns about the solvency of its main contractor, Carillion. With over 50% of the works still to be completed, the client wanted some advice as to how it could manage the risks (legally and practically) if the contractor did go “pop”. In January this year, the concerns became a reality. This blog addresses these key questions and what followed in the wake of Carillion’s demise. Continue reading

REUTERS | Rick Wilking

When I was a kid, Top Trumps were all the rage. I know from my own boys that they still are. Back then, it was all about whether you had the fastest car or the most popular footballer (even Star Wars characters featured, but how did you decide if Hans Solo was better than Princess Leia?). Now, just about every topic is covered by a set of cards.

I mention this because a recent TCC judgment demonstrates that the arbitration clause in the JCT standard building contract can “trump” a Part 8 application for declaratory relief, with the court granting a stay of those Part 8 proceedings. Continue reading

REUTERS | David Mdzinarishvili

A contract can be a long term commitment. Over the course of a contract, things happen. Circumstances change. Force majeure clauses generally allow parties to allocate contractual risk, by limiting liability, excusing performance or providing for termination, if unusual or unfortunate circumstances arise. However, the recent case of Seadrill v Tullow reminds us that it is not all that easy for a party to seek to avoid obligations it has freely undertaken. Continue reading

REUTERS | Denis Balibouse

It is the start of autumn and July seems a long way off now, with the summer holidays all over and the World Cup just a distant memory. Consequently, it may be easy to have forgotten about Vinci Construction UK Ltd v Beumer Group UK Ltd, which had its latest outing in the TCC at the end of that month. This time it was Jonathan Acton Davis QC (sitting as a deputy High Court judge) who enforced the adjudicator’s decision and dismissed Beumer’s (the sub-contractor) arguments that the adjudicator was in breach of the rules of natural justice.

I think that the interesting part of the case is the third natural justice argument (failure to disclose material) because it was very similar to (and based on) the natural justice argument that Vinci ran and succeeded with in the proceedings before Fraser J but, on this occasion, Beumer lost. Continue reading

REUTERS | Navesh Chitrakar

A client recently called me in a panic. Their contractor had discovered a protected species of bird had set up home in the exact spot where they needed to carry out the next phase of works at one of their sites. No one on site was entirely confident on what the appropriate next steps should be and so the client, concerned about the potential consequences, had immediately instructed the contractor to suspend works and asked me to investigate.  Continue reading

REUTERS | Navesh Chitrakar

I liked the classics at school and did rather well in them. When I last wrote about ICI v MMT, I referred to Hercules and Hydra. This time, I’m delving further into Greek mythology, with reference to Scylla and Charybdis, which is used in the context of the idiom “being between Scylla and Charybdis”. It means “having to choose between two evils” and is a bit like more well-known idioms such as “between the devil and the deep blue sea” and “between a rock and a hard place”.

It came to mind when I was reviewing some of Fraser J’s comments about the expert evidence in ICI v MMT. Continue reading

REUTERS | Gleb Garanich

Concurrent delay is something that the courts tell us is exceedingly rare. And yet, it is a subject which can occupy much time when parties are in dispute about entitlement to an extension of time.

The Court of Appeal has now considered whether parties to a construction contract can decide how to apportion risk in the event of concurrent delay. The question for the court was whether such clauses offend the prevention principle and cause time to be at large. Continue reading

REUTERS | Ricardo Moraes

For the first time in quite a while I am in the enviable position of having more than one adjudication enforcement case to choose to write about this week.  In the end I plumped for Beach Homes v Hazell and Hazell as it raises some interesting points about bespoke dispute resolution clauses. It is a judgment of Mr Jonathan Acton Davis QC, one of the army of Deputy High Court judges currently sitting in the TCC. Continue reading