In my previous two posts I provided an introduction to the Party Wall etc. Act 1996 (PWA 1996) and a brief outline on the agreement of a party wall award where a dispute arises.
In this third post I address some of the more complex aspects of the PWA 1996, including access rights, costs, expenses and special foundations.
Access
Development work often requires temporary access over a neighbour’s property. Such access can take a number of forms, including an oversailing crane or the erection of hoarding and scaffolding. Formal licence agreements for access are normally required because utilising another person’s land without obtaining their permission would constitute a common law trespass.
The PWA 1996 states that the building owner may enter onto an adjoining owner’s land “for the purpose of executing any work in pursuance of this Act”. This means that any notifiable works could allow a developer rights of entry regardless of their neighbour’s objections.
In fact, where access is unavailable, the building owner has the right (in the presence of a police officer) to break open any fences or doors to gain the authorised access. Further, any person who hinders or obstructs this access could be found guilty of a criminal offence and fined.
Making use of the PWA 1996’s access provisions requires the building owner to comply with the procedure in section 8. Entry onto the adjoining owner’s land or premises is only available if notice of the requirement is served at least 14 days in advance or, in case of an emergency, as much time as is reasonably practicable.
It is usually the appointed party wall surveyors who agree the extent of any access, taking into account whether the request for access will cause the adjoining owner unnecessary inconvenience (in which case they would consider whether there was any reasonable alternative way to carry out the work).
However, the PWA 1996 cannot grant access rights for works that are not notifiable. The distinction between what is and what is not notifiable can be small. For example, a scaffold erected to install a flashing (deemed notifiable) is likely to be permitted, but the same scaffolding remaining for any other purpose would require separate permission.
Where works are not notifiable under the PWA 1996, developers will find little to help them in the Access to Neighbouring Land Act 1992. While it gives building owners certain rights to enter onto adjoining land, this is only for repairs and maintenance (not development). In addition, building owners need to go to court to obtain an access order. Hence it is rarely used.
For non-notifiable work, securing access over neighbouring land may well include negotiating financial consideration with the land owner. In cases where the access is essential to a developer’s scheme, an adjoining owner can effectively hold the developer to ransom, and increasingly larger sums are being demanded from commercially aware neighbours.
Cost and expenses
In simple terms, the building owner is most commonly responsible for the cost of the works. However, the PWA 1996 does set out situations where costs may be apportioned differently. For example:
- The costs may be part payable by the adjoining owner if they have served a counter notice requiring certain additional works to be undertaken.
- The costs for the repair of a party structure can also be shared between the building and adjoining owner, depending on the:
- use which the owners make of the party structure; and
- the responsibility for the defect or want of repair.
Similarly, the surveyor’s costs for preparing a party wall award are normally included as an obligation to be paid by the building owner. However, this principle is not expressly enshrined within the PWA 1996, and the actual wording allows costs to be defrayed between the owners as the surveyors determine. For example, where an adjoining owner acts in such a way as to increase the cost of preparing an award, it should not necessarily be reasonable for that cost to be attributed to the building owner. This may come as a surprise to an adjoining owner, who may erroneously believe that the developer will meet all the costs.
If the surveyors require any specialist advice in order to complete their award, the principle of defrayment of cost also applies. This could be the engagement of an engineer or perhaps, in very limited circumstances, legal advice.
The general principle of including any legal fees within a party wall award appears to be supported by the judgment in Onigbanjo v Pearson. However, the main test is whether the costs are “reasonable”. In the majority of cases, this is unlikely to be the case. The administration of the PWA 1996 is placed in the hands of surveyors rather than solicitors and there is an expectation that they are able to fulfil the duties required of them without seeking legal counsel.
Enclosure costs
There are some scenarios where one owner may wish to make use of part of a building that their neighbour previously constructed and paid for. A common example is where one owner has erected a party wall, and the adjoining owner subsequently encloses upon the wall to facilitate their own development.
In such cases, the PWA 1996 makes an allowance for a fair proportion of this cost to be reimbursed. The enclosure cost (as it is called) should be based on current construction rates regardless of when the original structure (being enclosed upon) was first built. It is generally derived by calculating how much the entire wall would cost to complete and then splitting the cost evenly between the two owners. This figure should also make provision for any preliminaries, access and design costs.
Security for expenses
The PWA 1996 allows an adjoining owner (prior to the commencement of works) to serve a notice on the building owner requiring them to provide such security as may be agreed between them.
Security should be limited to situations where an adjoining owner may be exposed to costs as a result of the building owner’s works. Its purpose is to provide a safety net against liability, not to cover the ordinary possibility of damage. For example, security could be requested where the work involves the demolition and rebuilding of a party wall. It will protect the adjoining owner from the cost of rebuilding the structure following demolition, should the building owner fail to do so.
Although the request for security must come from the adjoining owner, it is often prompted by their appointed surveyor who should ensure that the adjoining owner is aware of their rights, highlighting where security is applicable, and how to facilitate a request. In the event of any dispute the matter is passed to the surveyors for determination.
The PWA 1996 does not specify what form of security should be used but, in practice, it generally takes the form of a cash sum placed in an escrow account under the authority of the two surveyors. Other less common forms could include:
- Specialist insurance policies.
- Bonds or guarantees.
- Property charges.
It is worth noting that security for expenses can also be requested by the building owner from the adjoining owner where the cost of the works is being split between them.
Special foundations
Section 20 of the Act defines “special foundations” as:
“… foundations in which an assemblage of beams or rods is employed for the purpose of distributing any load…”
In layman’s terms, this means that any foundation containing reinforcement will fall within the definition. It should be noted that the presence of dowels between underpinning bays would not constitute a foundation being “special”.
The difficulty with special foundations is that the PWA 1996 states they cannot be placed on an adjoining owner’s land without their express consent in writing. If that consent is withheld, the building owner must find alternative and often less practical methods of construction (such as a mass concrete foundations). In fact, a more slender reinforced foundation will often be beneficial for both owners, providing more valuable floor space within the building owner’s development, and that of the adjoining owner too if they subsequently also decide to make use of the wall.
In cities like London, with space at a premium, and the growing popularity of basement developments, reinforced foundations are becoming ever more common. Adjoining owners are also increasingly threatening to withhold consent as a means to frustrate a building owner’s proposals or to seek certain concessions.
The PWA 1996’s definition of “special foundations” is now generally considered to be outdated. The law was developed at a time when large grillage foundations were used. Consisting of a complex arrangement of steels, such foundations could create difficulties if the adjoining owner later wished to develop their own land.
Recent case law has cast some doubt on whether or not special foundation consent is required in every scenario. In Chaturanchanda v Fairholme, it was held that the adjoining owner’s express consent was not required for a section of reinforced concrete beneath the adjoining owner’s land. However, this decision was based on the specific method of construction and is not considered by the majority of surveyors to circumvent the requirement of consent generally. (For a more comprehensive review of the subject and the case in particular, see Stephen Bickford-Smith’s excellent review.)
Just the beginning
In most situations, the PWA 1996 can be applied in a straightforward and simple manner, despite the many nuances and peculiarities that can arise. Engaging a competent party wall surveyor is not just vital to avoid any potential pitfalls but they will also ensure that the developer (and their neighbours) make the most of the rights available to them.
I have read your article from last year, regarding the Party Wall Act and in particular dealing with the rights of access granted by s8 of the Act, and I would appreciate your thoughts on the following: As you mention, s8 of the Act gives the Building Owner rights of access “for the purpose of executing any work in pursuance of this Act”. You state that a Building Owner is therefore allowed access in relation to “notifiable works”. S6 of the Act applies in relation to “Excavation and Construction” within 3m of the adjoining owner’s building, and specifically states that it applies where the BO plans to (a) excavate or (b) “to excavate and build a building or structure”. The party wall surveyor has advised that the right of access to the adjoining owner’s land only extends to allow access for the purposes of carrying out the excavation work, and does not allow access for the purposes of carrying out the subsequent construction of the “building or structure”. This seems contrary to the wording of s6 which specifically refers not only to “excavation”, but also, as a separate subclause, excavation and building.
In short, the question really is: where a s6 notice has been served, does s8 grant a building owner access to the adjoining owner’s land for the purposes of constructing the wall of a building (where the foundations of that wall extend below the foundations of the adjoining owner’s foundations – and hence the application of s6), or does s8 only allow access for the excavation element of the work?
I’d be very interested in hearing the response to Stewart Cole’s question since this is a live situation with my neighbour (BO) who will require access to my land to build an extenstion that I objected to and I wish to legally deny him access
Section 8 refers to entering and remaining on land or premises “for the purpose of executing any work in pursuance of this Act”. That covers works carried out under sections 1, 2 and 6.
You should ensure there is a party wall award, as this can then set out what is necessary to enable the building owner to carry out its works.
You will be unable to prevent the building owner from entering your land, provided the correct notice is served and that entry is used to carry out works covered by Act (as set out in the party wall award). Section 16 provides that it is a criminal offence to do so, which can be tried in the magistrates’ court.
l understand that no equipment can be brought onto the neighbours land by the builder not even a trowel. is this correct, possibly health and safety issues, they cannot be stopped to entering the property
My elderly neighbour has gone into a nursing home. Yesterday I heard a very nasty man shouting at a woman. I went round to see if she was ok. It turned out it was the son in law of the elderly lady who was e trembly aggressive. We are having building works done & I informed the daughter of the older lady ( nasty Mans wife). He started saying I needed a party wall act for putting up scaffolding for my detached house which isn’t on their land and for which we need no access on to his mother-in-laws. I am worried now that the scaffolding bars may poke over her fence a little into the air. I was not rude or retaliatory against him. He said my architect should of told me. He doesn’t own the property but I’m sure his wife who looks shattered has power of attorney. Previous owners had scaffolding erected before with no party wall act. We are replacing the leaking roof. I didn’t sleep last night worried for both myself and for his wife.
Building Owner ‘A’ builds a single storey extension up to the line of junction/boundary and the external wall sits wholly within their property.
Building Owner ‘B’ wants to enclose their single storey extension and use the external wall of Building Owner ‘A’. They are prepared to pay enclosure costs and the wall is used.
Therefore a situation as defined in 20(b) of the Act has been created.
Sometime later Building Owner ‘A’ wants to raise a second storey and use the wall.
The original wall is wholly inside their boundary but what is the status of the wall above the party wall which has been created when the single storey extensions were built? Would they be able to do it and have access rights under the Act? Are there any cases where this has been decided?
If you consult the drawings in the DCLG’s explanatory booklet, you will see diagram 4 deals with this. As the guidance explains (on page 5), only the part of the wall that does the separating is “party” – sections on either side or above are not “party”.
Hi,
I have a party wall agreement for our side return extension. We’ve erected the necessary hoarding on our neighbour’s property with his agreement and are in the process of erecting the walls for the building.
However, he has now requested on Friday evening that we must remove all the hoarding on Monday as he has builders coming in.
Is this a reasonable request?
Our builders feel it would be unsafe due to depth of excavation for foundations and for them to continue works in a secure environment.
Do we have any legal right to request 2 weeks notice?
Hi, my house which is grade II listed, built 1780 shares a wall with premises built much later and is built off my wall. About 15 years ago consent was given for the next door premises for a telecommunications tower on its flat roof which I opposed at the time. Just recently, the flat roof has needed to be strengthened due to the loading of the towers and steels and concrete have been loaded onto this flat roof but not yet put in place due to my intervention. I have hired a party Wall expert and Mech Eng. I am concerned about the additional loading on my wall and don’t wish to agree to this taking place. Can I refuse this ?
Thanks
James’ first blog, Introduction to party wall issues, may assist. It states:
“It should be made clear to the adjoining owner that the PWA 1996 exists to facilitate and not hinder development and it regulates notifiable works, not the whole development scheme … Disputes and litigation can be avoided by thoughtful negotiation, which may be conducted by surveyors appointed to give consultancy advice.”
If materials are loaded; steels and concrete on a flat roof for proposed works on that roof which sits on a party wall. If PW notification has not been served on the neighbour, don’t the new materials breach PW notification by putting loads onto the party wall without consent?