All posts by Practical Law Construction

REUTERS | Jean-Paul Pelissier

On 1 May 2019, the statutory adjudication procedure introduced by the Construction Act 1996 will have been in force for 21 years. At the risk of over-egging an analogy, its life so far has followed a pattern familiar to parents:

  • In its infancy it had a devastating effect on many relationships.
  • As a toddler it thought it could do no wrong (see Macob v Morrison).
  • As it approached its teens it had an alarming and confusing growth spurt (particularly following the amendments in the LDEDC 2009).
  • Now, as it reaches maturity, it appears to be trying to shed some of its less attractive features (for example, see S&T v Grove Developments).

Grove was the first case in which a real fetter was recognised on the statutory right to refer a dispute to adjudication at any time. In that case, the Court of Appeal upheld Coulson J’s first instance decision, confirming that the employer could start an adjudication to dispute the true value of the works for which the contractor had claimed an interim application for payment, even though the employer had not served a valid pay less notice. However, the employer could not do so until after it had paid the notified sum due as a result of the failure to serve the notice.

The meaning and effect of Grove was considered recently in M Davenport Builders Ltd v Greer, where Stuart-Smith J was asked to enforce a “smash and grab” adjudication decision in connection with a building in Stockport.

Continue reading

REUTERS |

A tenant client was recently surprised by a clause in its agreement for lease (AFL). The clause allowed the landlord to defer the target access date and long stop date commensurate with any extension of time granted by the Employer’s Agent (EA) under a JCT Design and Build contract for the landlord’s works.

It was the first time that the client had entered into an AFL so this was new territory for them. When they spotted the reference to the EA granting extensions of time, alarm bells started to ring.

Surely, they said, the very nature of the role of EA meant that when it came to taking any decisions under the building contract they would act in the landlord Employer’s favour? What if the EA decided to grant an extension of time under the building contract to postpone the access date and long stop date for the landlord? This delay would have serious consequences for the tenant. Not only in terms of serving out the notice period on its current tenancy but also in delaying the start of its planned works where its contractor was geared up and ready to go. What on earth could they do?

Don’t worry, we said: it will be fine. Here’s why. Continue reading

REUTERS | Ali Hashisho

Lingchi, also known as known as death by a thousand cuts, was a form of torture and execution used in China. According to Wikipedia, it may not have involved as many as 1,000 cuts, that would depend on the crime, the executioner and whether the family could afford a bribe to speed up the process (and reduce the number of cuts).

Finding myself increasingly involved in serial adjudication, I realise that it can be a valuable and efficient way to resolve disputes, particularly with sophisticated parties and their representatives. However, I sometimes feels like certain parties use the process to wear the other down. Hence the reference to lingchi!

The reason I mention this is because of Stuart-Smith J’s judgment in Hitachi Zosen Inova AG v John Sisk & Son Ltd, where the key issue was whether the dispute referred in the eighth adjudication was the “same or substantially the same” as the dispute referred in the second adjudication. Continue reading

REUTERS | Leonhard Foeger

It is well known that practical completion is often easier to recognise than it is to define, which is why the Court of Appeal’s judgment in Mears Ltd v Costplan Services (South East) Ltd and others is an important read for construction practitioners.

It was an appeal from Waksman J’s December 2018 judgment, which was dismissed, and is the first time in 50 years that the Court of Appeal has considered the meaning of “practical completion”. Continue reading

REUTERS |

2014 was a simpler time. England crashed out of the World Cup in the group stages, a robot made the first ever landing on a comet, and the European Medicines Agency (EMA) signed a 25-year underlease (the lease) with the Canary Wharf Group for its headquarters in London.

Three years later, the Prime Minister formally invoked Article 50. This began the legal process of British withdrawal from the European Union. Citing Regulation 2018/1718, EMA relocated its London office to Amsterdam and wrote to Canary Wharf, informing them that it would treat Brexit as a frustration of the lease. Aggrieved by this decision, Canary Wharf sought a High Court declaration that the lease would not be frustrated by Brexit.

Why does this case matter to the construction industry? Because it concerns a decision on the rarely used doctrine of frustration, and the judgment contains a very useful summary of the principles of frustration that are equally applicable to construction contracts. Continue reading

REUTERS | Darrin Zammit Lupi

When I wrote about Coulson LJ’s judgment in Bresco  v Michael J Lonsdale, Cannon  v Primus back in January, I said that I thought the waiver points applicable to jurisdictional reservations were:

“… of greatest use to parties and those representatives who deal with adjudications on a day to day basis. After all, how often do adjudications involve insolvent parties? I certainly haven’t dealt with one for some time now. By contrast, I see general (and specific) reservations all the time.”

Fast-forward two months and it seems that, for once, my crystal ball skills are effective, as O’Farrell J has applied Coulson LJ’s principles on the reservations a party made (both general and specific) on two occasions: Ove Arup v Coleman Bennett and Donald Insall Associates Ltd v Kew Holdings Ltd. Continue reading

REUTERS | Regis Duvignau

Imagine this: a contractor undertakes to perform certain works by a specified date, and agrees to pay liquidated damages (LDs) if it does not complete by that date (subject to any entitlement to an extension of time). The contractor, through its own fault, is late and does not complete by the specified date. In fact, the contractor is very late and, in the end, the employer terminates the contract before the works are completed (as it is entitled to do under the contract).

For those of us involved in the construction industry, this scenario does not require too much imagination.

In my previous blog post, I said that whether LDs could be recovered after termination of the contract would appear on my hypothetical construction law exam paper. I was concerned about how and whether the unlucky student sitting this exam question would get to the right answer.

It turns out that there was a more fundamental problem – I asked the wrong question. The recent Court of Appeal decision in Triple Point Technology Technology Inc v PTT Public Co Ltd shows that I should have asked whether LDs are recoverable at all in the event of termination.  Continue reading

REUTERS | Amit Dave

It’s over a year since the second editions of the Rainbow Suite were published and the recent conferences in London and the Middle East provided a forum to reflect on the changes. Indeed, this was reflected in the respective agendas. There were sessions dedicated to responding to commentary on the second editions and also to comparisons with other “international” standard forms. Errata for the Second Editions were also published in December 2018, picking up on largely typographical points.

One year on, the conversation has changed from considering the changes from an academic, theoretical perspective to whether and how they might be applied in a more practical context. Understandably, given the extent of the changes in the second editions (particularly when compared, for example, to the “light touch” approach adopted by NEC in the NEC4 update, and its subsequent round of amendments), it is still early days. However, there are indications that the first contracts based on the second editions have been awarded – or at least are being seriously considered for new projects. For most, though, the benefits of greater clarity and certainty that the drafters have sought to provide are still being evaluated against the consequential increase in complexity and decrease in flexibility, and the advantages of using the tried-and-tested 1999 forms.  Continue reading

REUTERS | Ilya Naymushin

A few weeks ago I was finishing a paper on fraud, which was based on a SCL talk that I’d given a little while before. Some of you may have been there. I have to confess that it is a lot easier blogging than it is writing one of those papers: the word count is a killer! Anyway, I digress. The reason I’ve mentioned my paper is because, just as I was getting to the end of it, Alexander Nissen QC’s judgment in BM Services Inc Ltd v Greyline Builders Ltd became available and fraud was a key issue in the enforcement proceedings that he dealt with.

I thought I’d better take a look and share my thoughts on what I think is a good example of the courts applying established guidance in cases of fraud and adjudication. Think cases like SG South v King’s Head Cirencester, Speymill Contracts v Baskind, GPS Marine v Ringway and, most recently, Gosvenor v Aygun, which all tell us that there is a difference between an issue that was or could have been decided in the adjudication, and an issue raised for the first time in enforcement proceedings.

There is also some interesting stuff in there about adjudicators’ fees and it is, I think, a good example of the TCC’s continuing supporting for adjudication. Continue reading

Share this post on: