What does the Technology and Construction Court’s (TCC) annual report for 2009-10 tell us about the work of the court?

The TCC – a court for complex cases

Concurrency (and promiscuity) in the TCC
I don’t know about you, but I often find that the introduction to a TCC judgment sets the tone of the dispute and (I’m embarrassed to say) influences whether I read the entire judgment or simply pick out the interesting bits and then turn to the end for the result.
I was certainly encouraged to read the entirety of Coulson J’s judgment in Jerram Falkus v Fenice Investments when I discovered that the parties had been “…extraordinarily promiscuous in their attempts at dispute resolution…”. (I have previously blogged on the parties’ dispute over the adjudicator’s fees in one of three adjudications that took place.) Continue reading

Ask the team: do the adjudication provisions of the Scheme always apply wholesale under the Construction Act 1996 (as amended)?
What happens if a construction contract fails to comply with the adjudication requirements of the Construction Act 1996 (as amended)?
In particular, what if a Tolent clause offends the Construction Act 1996 (as amended)? Will the Scheme for Construction Contracts 1998’s adjudication provisions replace all the contractual adjudication provisions? Continue reading

Requesting more time after the riots
Last week I received a request from the solicitors for one of the parties in an adjudication to have more time to serve a submission. What made this request stand out was the reasons given, “because of the riots”. It isn’t a common reason, I’m pleased to say.
Of itself, a request for more time is not unusual. Such requests come in quite regularly from the parties or their representatives. It is a question of natural justice really. Continue reading

Contract is king but it’s so unfair
The facts in Costello v Macdonald are not uncommon in the construction industry, when a party wants to redevelop a site that it owns:

Assessing the evidence and using your own judgment
As I said previously, when I read Edwards-Stuart J’s judgment in Hyder v Carillion, two things struck me:
- The court confirming that it is the decision of the adjudicator that is binding, not his reasoning.
- The question an adjudicator should ask himself as to whether he should share or put his approach or interpretation to the parties?
This post considers the second point. Continue reading

It’s all in the adjudicator’s decision, or is it?
When I read Edwards-Stuart J’s judgment in Hyder v Carillion, two things struck me:
- The court saying that it is the decision of the adjudicator that is binding, not his reasoning.
- The question an adjudicator should ask himself as to whether he should share or put his approach or interpretation to the parties?
This post considers the first point. I’ll save the second, “walking a tightrope” point, for another day. Continue reading

JM Keynes, The End of Laissez-Faire:
“The important thing for Government is not to do things which individuals are doing already, and to do them a little better or a little worse; but to do those things that at present are not done at all.”
Last month we were still awaiting an effective date for the Construction Act 1996 changes. Now we know that 1 October 2011 is D-day in England and Wales, and 1 November in Scotland. We also know about the changes to the Scheme for Construction Contracts 1998 (and its Scottish equivalent), with three different versions (for England, Wales and Scotland). At least there is consistency in the Exclusion Order that each country has published, but yes, we have three of those too. Continue reading

Insurers back on the hook for third party claim
In November 2010, I reported on the TCC’s decision in McIlroy v Quinn. That judgment had flagged up yet another problem for a claimant seeking to take advantage of the Third Parties (Rights Against Insurers) Act 1930 (1930 Act). On 18 July 2011, the Court of Appeal described the TCC judgment as “remarkably unfair” and, crucially, wrong in law.

…where should I start?
If you are a construction lawyer or a commercial manager who needs to understand how the changes to Part II of the Housing Grants, Construction and Regeneration Act 1996 (Construction Act 1996, also known as the HGCRA 1996) will affect construction contracts, this Ask the team gives you the basics, based on PLC Construction’s materials. In particular, we suggest a draft agenda that can be used for a training session. Continue reading