REUTERS | Ognen Teofilovski

Ask the team: What are provisional sums?

Provisional sums are a mystery to many construction and engineering lawyers, often thought of as the domain of quantity surveyors, rather than legal advisers. In fact, a building contract’s treatment of provisional sums can have a profound impact on the overall cost and speed of a project.

What is a provisional sum?

There is no single agreed definition of the term “provisional sum”. In general, it refers to a price for work that may not be required, or whose scope is undefined. In either case, the parties do not try to price it accurately and simply include a provisional sum as their “best guess”.

When are provisional sums used?

Provisional sums are often used in two situations:

  • Where the precise details of a part of the works is not finalised. For example when part of the site is hidden (perhaps underground or within the fabric of a building) and cannot be fully investigated prior to commencing the works.
  • Where a project involves specialist sub-contractors. For example, a project that utilises new technology, which is impossible to price accurately in advance.

Getting from a provisional sum to an actual price

The precise meaning and effect of a provisional sum depends on what the parties agree in their contract. A commonly agreed position is that, as the works proceed, the provisional sums will be replaced with valuations of the actual work done. In this way the final cost may, in theory, go down as as well as up. (The parties should make it clear that the provisional sum will be replaced by the actual cost of the work, otherwise the contractor may argue that it is entitled to the provisional sum plus the actual cost.)

In addition to price, the parties should agree the effect on the project programme of carrying out (or not carrying out) works priced under a provisional sum. However, there is less common ground on how this should be done.

The JCT approach

The JCT adopts the RICS Standard Method of Measurement, seventh edition (SMM7) when dealing with provisional sums. Perhaps the most important feature of SMM7 in this regard is its distinction between “defined” and “undefined” provisional sums.

A “defined” provisional sum relates to work whose details are known (SMM7 sets out the required details in General Rule 10.3). The contractor is deemed to have made due allowance for defined work in its programming, planning and pricing preliminaries (General Rule 10.4).

In contrast, “undefined” provisional sums relate to work where the employer is unable to provide detailed information and the contractor is not deemed to have made allowances for it in its price or programme (General Rule 10.6). In short, a contractor’s entitlement to an extension of time and/or indirect costs for a provisional sum depends largely on whether it is defined or undefined.

ICE and FIDIC

Like the JCT, the ICE Conditions of Contract, seventh edition and FIDIC’s Red Book both define provisional sums and include provisions for valuing them. However, neither of those two forms of contract are entirely clear about the relationship between a provisional sum and the project programme. Although there are extension of time provisions that may assist a contractor in some situations, these will not always apply.

The risks of using provisional sums and the NEC3 approach

The variety of approaches adopted in the standard forms of contract illustrates the need for great care when dealing with provisional sums. Even on a purely commercial basis, using a provisional sum creates uncertainty, both for the employer and the contractor. For this reason it is best practice to use them sparingly, so that they make up only a small part of a project.

The seriousness of these risks is illustrated by the fact that the NEC3 Engineering and Construction Contract (ECC) does not mention provisional sums at all. The NEC website justifies this by stating that “if you cannot precisely define aspects of the works, you should not be including them as a provisional sum…”. That is a stark warning to all construction practitioners of the risks inherent in using provisional sums.

20 thoughts on “Ask the team: What are provisional sums?

  1. At the moment I am pursuing a Quantity Surveying course and this post helped me to finish one of my assignments.

  2. At the moment I am pursuing a Quantity Surveying course and this post helped me to finish one of my assignments.

  3. If only I had read this before signing a contract… avoid provisional sums at all costs they’ve just cost me 26k off the job I shook on.

    1. the provisional sum provision can reduce the possibility of claims by keeping a certain amount in contract price for items whose specs/details are not yet clear.

  4. If only I had read this before signing a contract… avoid provisional sums at all costs they’ve just cost me 26k off the job I shook on.

  5. Is it necessary to have the list and break-down of prices for the provisional sum items under the FIDIC contracts.

  6. Is it necessary to have the list and break-down of prices for the provisional sum items under the FIDIC contracts.

  7. I’m afraid we can’t answer individual questions on our blogs – apologies. Provisional sums are usually addressed by a specific clause in a FIDIC contract, see for example clause 13.5 of the Pink Book.

  8. I’m afraid we can’t answer individual questions on our blogs – apologies. Provisional sums are usually addressed by a specific clause in a FIDIC contract, see for example clause 13.5 of the Pink Book.

  9. Can the quantity surveyor or engineer, change a fixed item on PG’s to Provisional sum??

  10. Can the quantity surveyor or engineer, change a fixed item on PG’s to Provisional sum??

  11. In a contract where the contractor is expected to cover the consultant accommodation with provisional sum of payment per month can the payment approving engineer has the right to ask for detailed expense justification testimonials before approval?

  12. In a contract where the contractor is expected to cover the consultant accommodation with provisional sum of payment per month can the payment approving engineer has the right to ask for detailed expense justification testimonials before approval?

  13. A provisional sum is an allowance, usually estimated by the cost consultant that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to price.

    Is there any percentage for PS sum?

  14. This post is really very helpful for understanding the basic idea of the provisional sum in construction contracts.

  15. As per fidic 1987 cl 58, I am not clear on procedure to be followed for disbursement to the contractor (not nominated contractor) specially when he get services from other parties. His cost agreed with the party include markup by that party and so the contractor cannot be given second time. Can you please clarify your view point.

  16. When the item of work in the Provisional Sum is executed by a utility agency or by a sub contractor, the mark up on PS item to be paid to the main contractor, what are the duties and responsibilities of the main contractor?

  17. We just had a tender and tenderers submitted their offer while doingthe tender report the engineer stated that one provisional item should be increase. Since we are still on doing the tender analysis, we will again ask the tenderers to re-evaluate their rates and qualifications then re-submit an offer. My question is can we change the amount of one provisional item when they re-submit?

  18. When there is a provisional sum in your bill of quantities and work is done towards the specific line item and it was not specified for example in a design process when can you claim these funds?

  19. Just put a tag in the tender clarifying that all provisional sums are considered to be “undefined”. Then there can be no argument. In any case before even tapping into a PS, you need to talk to the client and ensure you have their express acceptance in writing to use the PS. In reality they will generally get a contractor to price a VO for the PS item and consolidate the total of VO’s against the allowed PS’ at the end of the contract. No one likes headaches..

Comments are closed.

Share this post on: