Monthly Archives: June 2019

REUTERS | Hannibal Hanschke

The idiom “all duck or no dinner, if you’re not familiar with it, means “all or nothing. I once worked for a partner that was quite fond of using it, particularly in the context of limitation periods and time bars: if you’re in time, your clients will usually have a smorgasbord of dispute resolution options open to them. If you’re out of time, they go hungry.

Construction contracts often include clauses requiring a party to notify the other party within a specified time if it wishes to make a claim. In some cases, time-bar notice provisions are more than a mere obligation, rather they are a condition precedent to a valid claim.

We are frequently advising clients about conditions precedent in construction contracts, particularly in relation to timely notices for extensions of time and/or loss and expense (for example, under a JCT contract) and compensation events (for example, under an NEC contract). But what about notice requirements for referring a dispute to adjudication? We can often fall back on the position under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act), being that disputes may be referred to adjudication “at any time”. If the Construction Act doesn’t apply, the parties may agree to limit that right. Continue reading

REUTERS | Phil Noble

We will all be familiar with the questions asked and answered by solicitors in the lead up to the purchase of a house. For commercial property the same process is carried out but the stakes, at least financially, can be even higher. Pre-contract correspondence between solicitors can be a fertile ground for possible misrepresentation claims if a development does not go well.

The recent case of Wilson & Sharp Investments Ltd v Falmouth Property Investments Ltd raises some interesting points of law concerning misrepresentation claims, particularly between developers, and also important issues of procedure for summary judgment applications. Continue reading

REUTERS | Jonathan Drake

Earlier this year I found myself waiting for the Court of Appeal to bring the next instalment in a series of interesting decisions regarding subrogation claims in insurance disputes (not a contradiction in terms, I promise!), which I and my colleague John have been taking it in turns to blog about (see Joint insurance and rights of subrogation revisited and Co-insurance and subrogation rights revisited (again!)). Unfortunately (though perhaps not for those involved) the case in question (Haberdashers‘ Aske’s Federation Trust Ltd v Lakehouse Contracts Ltd and others) settled.

But it feels as though there’s been a missed opportunity to answer a question that was left entirely open in Gard Marine and Energy Ltd v China National Chartering Company Ltd: where there is a co-insurance policy in place and a sub-contractor causes loss, if the co-insurance policy (for whatever reason) does not cover the sub-contractor, can the insurer bring a subrogated claim against the sub-contractor or, does it first have to prove the sub-contractor is liable for the loss?    Continue reading

REUTERS | Maxim Shemetov

Picture this scenario. The parties’ contract provides that when there is a dispute, an adjudicator is to be appointed from a panel of three, which the parties have already agreed on. In the alternative, if the parties cannot agree the identity of the three panel adjudicators, they will be nominated by the President of the Chartered Institute of Arbitrators (CIArb) as the adjudicator nominating body (ANB). In the event, the parties fail to agree on who the three should be, and then one of them is unhappy with who the CIArb selects.

This scenario played out before Jefford J earlier this year. It was, in effect, a dispute about a dispute, but led to some interesting comments from the judge about adjudicator nomination.

Continue reading

Share this post on: