Monthly Archives: September 2018

REUTERS |

Last year, a developer client raised concerns about the solvency of its main contractor, Carillion. With over 50% of the works still to be completed, the client wanted some advice as to how it could manage the risks (legally and practically) if the contractor did go “pop”. In January this year, the concerns became a reality. This blog addresses these key questions and what followed in the wake of Carillion’s demise. Continue reading

REUTERS | Rick Wilking

When I was a kid, Top Trumps were all the rage. I know from my own boys that they still are. Back then, it was all about whether you had the fastest car or the most popular footballer (even Star Wars characters featured, but how did you decide if Hans Solo was better than Princess Leia?). Now, just about every topic is covered by a set of cards.

I mention this because a recent TCC judgment demonstrates that the arbitration clause in the JCT standard building contract can “trump” a Part 8 application for declaratory relief, with the court granting a stay of those Part 8 proceedings. Continue reading

REUTERS | David Mdzinarishvili

A contract can be a long term commitment. Over the course of a contract, things happen. Circumstances change. Force majeure clauses generally allow parties to allocate contractual risk, by limiting liability, excusing performance or providing for termination, if unusual or unfortunate circumstances arise. However, the recent case of Seadrill v Tullow reminds us that it is not all that easy for a party to seek to avoid obligations it has freely undertaken. Continue reading

REUTERS | Denis Balibouse

It is the start of autumn and July seems a long way off now, with the summer holidays all over and the World Cup just a distant memory. Consequently, it may be easy to have forgotten about Vinci Construction UK Ltd v Beumer Group UK Ltd, which had its latest outing in the TCC at the end of that month. This time it was Jonathan Acton Davis QC (sitting as a deputy High Court judge) who enforced the adjudicator’s decision and dismissed Beumer’s (the sub-contractor) arguments that the adjudicator was in breach of the rules of natural justice.

I think that the interesting part of the case is the third natural justice argument (failure to disclose material) because it was very similar to (and based on) the natural justice argument that Vinci ran and succeeded with in the proceedings before Fraser J but, on this occasion, Beumer lost. Continue reading