Monthly Archives: June 2018

REUTERS | Tim Wimborne

Last summer I wrote about Fraser J’s “89-page opus” in Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd (or ICI v MMT). This week, my attention turns to his latest 95-page opus between the same parties. Last year the judgment was all about liability (which MMT won). This time, it was all about the numbers (which MMT won again). Jonathan also looked at the expert evidence points last time around, and may well do so again given some of the choice remarks, particularly about ICI’s quantum experts!

The judgment raises some interesting points, not least one of Fraser J’s final remarks (which you may notice I’ve borrowed for my title):

“This litigation also stands as something of an advertisement for adjudication.” Continue reading

REUTERS | Thomas White

Don’t wind me up

In Victory House General Partner Ltd, Re A company, Morgan J dismissed a petition to wind up Victory House, the employer under a building contract with RGB P&C Ltd, following its failure to pay a sum due to RGB pursuant to an adjudicator’s decision.

The case is the most recent of a number of authorities that make clear that it will only be in relatively rare circumstances that the presentation of a winding up petition will represent the most appropriate way to enforce an adjudicator’s decision. Continue reading

REUTERS | Toby Melville

Increasingly, the construction industry model that we know so well – based on layers of contractors and sub-contractors – is being called into question. In the last six months various failures (including Grenfell, Scottish PFI-built schools and Carillion’s collapse) have prompted questions about construction industry outsourcing and transfer of risk.

Queries have been raised about the potential for “passing the buck” and lack of accountability when things go wrong. On major construction projects, typically the large majority of the workforce are sub-contractors, sub-sub-contractors or workers employed on a daily or hourly basis, rather than being directly employed by the contractor. Does this model enhance the risk of non-payment, safety issues and reduced acceptance of responsibility for such issues? Continue reading

REUTERS | Darren Staples

You may recall that back in November I blogged about the UK government’s review of the 2011 amendments to the Construction Act 1996, and I revisited the topic after the consultation closed in January. The results of the consultation have not been published and the relevant page of the BEIS website does not give an indication of when they might be published; rather, it simply states that “We are analysing your feedback”.

However, I was interested to see that the UK is not the only country reviewing its security of payment legislation, and that John Murray has published his review of the Australian legislation, “Building Trust and Harmony”.

I should begin with a confession. I’ve not read the whole of the report but, in fairness, it is 350 pages long and includes 86 recommendations, so it is a mammoth piece of work. I thought that I would take a look at just a few of those recommendations in this week’s blog. Continue reading

REUTERS | Pascal Rossignol

The NEC contract is built on the spirit of mutual trust and co-operation. One area in which this plays out is in the context of applications for an extension of time or a change in the prices by a contractor. The project manager is required to assess these applications on a prospective or forecasted basis, at the time the relevant compensation event occurs.

However, one issue that the courts have not yet fully grappled with is how that assessment works when the contractual mechanism relating to quotations is not followed and the time and money effects of the compensation event fall to be considered after the impact of the event has played out. This post considers that scenario in the context of two recent cases: Northern Ireland Housing Executive v Healthy Buildings (Ireland) Ltd and Fluor v Shanghai Zhenhua Heavy Industry Ltd. Continue reading

REUTERS | Alexandre Meneghini

Sometimes the old cases are the best ones and that surely has to be true of the Ikarian Reefer. Even now, over 25 years since the judgment at first instance was handed down (and countless other pieces of guidance have been published) we still see experts getting it wrong.

I’m not sure if anyone remembers what the case was about (I certainly didn’t) but, even without looking it up, I’d have guessed it was a shipping case (the clue is in the name!). Continue reading

Share this post on: