Monthly Archives: December 2014

REUTERS | Sharif Karim

Jane Austen, Sense and Sensibility:

“Lady Middleton… exerted herself to ask Mr Palmer if there was any news in the paper. ‘No, none at all,’ he replied, and read on.”

It is often said that today’s news is tomorrow’s fish ‘n’ chip paper (even if only metaphorically, since they use white paper nowadays!). Whether that can ever be said about court judgments is debatable but, in the last two months, we have seen two landmark adjudication enforcement decisions.

Last month it was all about Eurocom v Siemensthis month was all about ISG v Seevic. If you missed Edwards-Stuart J’s judgment, we now know that failing to serve a pay less notice means the employer has agreed the value of the works the contractor is claiming for on an interim basis. If an adjudicator is asked to confirm that, a second adjudicator cannot then value that interim claim. Jonathan Cope explained some of the practical implications. Continue reading

REUTERS | Stephen Hird

Abraham Lincoln:

“Let me not be understood as saying that there are no bad laws, nor that grievances may not arise for the redress of which no legal provisions have been made. I mean to say no such thing. But I do mean to say that although bad laws, if they exist, should be repealed as soon as possible, still, while they continue in force, for the sake of example they should be religiously observed.”

The second half of 2014 has seen a number of important decisions affecting construction and engineering practitioners.  Continue reading

REUTERS | Yuriko Nakao

It was Max Abrahamson who famously once wrote:

“A party to a dispute, particularly if there is arbitration, will learn three lessons (often too late): the importance of records, the importance of records and the importance of records. It is impossible to exaggerate the extent to which lawyers can find unexpected grounds, often quite real, on which to cast doubt on evidence if it is not backed by meticulously established records.”

Following ISG Construction v Seevic College, parties wishing to defend claims for sums allegedly owed under construction contracts should focus on the importance of notices, particularly payment and pay less notices. Continue reading

REUTERS | Vasily Fedosenko

Following business as usual this week, Practical Law Construction will send its last email of 2014 next week, to arrive in your inbox on Wednesday 24 December 2014. We are then taking a break until the new year.

The first email of 2015 will be sent to arrive in your inbox on Thursday 8 January 2015. This email will include reports of all developments since 23 December 2014, as well as Practical Law’s looking forward to 2015 pieces.

Merry Christmas and a happy new year.

REUTERS | Toby Melville

I have to confess to having a small chuckle to myself when I read Edwards-Stuart J’s comments in Harding v Paice about how the third adjudication appeared to be “a model of how an adjudication should not be conducted”. This didn’t seem to be a reflection of the adjudicator, who the judge had “considerable sympathy for”, but how the referring party had conducted itself. For example, the judgment refers to a considerable volume of material put before the adjudicator, hundreds of pages of authorities, electronic copies provided when the adjudicator wanted hard copies and a refusal to extend the 28 days to 42 days because the referring party thought it had an “open and shut matter” (which the adjudicator clearly did not agree with). I’m sure many of us will share the judge’s sympathy for the adjudicator, as we’ve all been there in one way or another.

However, aside from procedural issues, the stand out issue for me is that this judgment demonstrates how the new payment regime has affected adjudication. Continue reading

REUTERS | Toby Melville

A claim for interest will often be the first remedy sought in the event of late payment. As such, it is an issue close to the hearts of contracting parties. It is also often an area of confusion in the Gulf region given the general prohibition on the levying of interest under Islamic Sharia law, the underlying framework of the Gulf legal system.

In this final part of a three-part blog series, considering some key issues in the context of the Qatari and UAE construction markets, we look at how interest is dealt with under UAE and Qatari law. We have previously looked at liquidated damages (LDs) and time bars. Continue reading

REUTERS | Lisi Niesner

Edwards-Stuart J has recently held that main contract adjudication provisions were not incorporated into a sub-contract. As a result, the appointed adjudicator had jurisdiction to deal with the dispute over the non-payment of Inviron’s application for £643,283.

Imtech Inviron v Loppingdale Plant

Loppingdale was appointed under a framework agreement to carry out various infrastructure works at Stansted Airport. It sub-contracted certain M&E works to Inviron.
A dispute arose as to payment under an interim application, which was referred to adjudication. Inviron obtained a decision in its favour from an adjudicator appointed by TECBAR, Mr Ben Sareen, for more than £600,000. Loppingdale refused to pay, contending that the adjudicator had not been properly appointed. Continue reading

REUTERS | Tobias Schwarz

When advising on a home project there has never been a “right” answer to the question of which contract to choose. As is so often the case, the choice of contract should be governed by the needs of the parties and the project.

To date, domestic parties have had to look to the JCT’s home owner/occupier contracts or those produced by bodies like the Federation of Master Builders (FMB). Alternatively, they have relied on the JCT’s Minor Works Building Contract (or even more sophisticated contracts from the JCT suite).

Last month, RIBA published two new contracts, the Concise Building Contract 2014 and the Domestic Building Contract 2014. As the titles imply, the first is for simple commercial building work (and is unsuitable for non-commercial work, such as work done to someone’s home). In contrast, the second is suitable for domestic work including “renovations, extensions, maintenance and new buildings”, but is unsuitable for commercial works.

So, with a new domestic contract in the market, are things about to change and, if they do, what does it mean for those parties that end up in a dispute with their builder?

Continue reading

Share this post on: