Monthly Archives: June 2013

REUTERS | Navesh Chitrakar

Robert Louis Stevenson, A Christmas Sermon:

“To be honest, to be kind – to earn a little and to spend a little less…”

These words may have been written at the end of the nineteenth century but still ring true today, especially in light of the Chancellor’s latest spending review. While he may argue he has “…taken our economy back from the brink of bankruptcy…”, it may not feel like that for the many affected by the latest round of cuts. However, one area to benefit was infrastructure, with the focus on capital investment in transport infrastructure. Another was energy. Earlier in the month, the Treasury had reported on infrastructure costs and we saw further guidance on development consent for infrastructure projects. It seems infrastructure is flavour of the month, for a month at least. Continue reading

REUTERS | Navesh Chitrakar

Did you realise that there are a multitude of different types of surveyors? Not just the usual suspects such as land surveyors (those standing by the side of the road in high-vis jackets with theodolites) and quantity surveyors (the “brick counters”), but also arts and antiques surveyors, machinery and business assets surveyors, and so on. Some surveyors even go on to specialise within their particular area. This may not be the most exciting start to a blog but bear with me.

Anyway, the different types of surveyors got me thinking about which roles (in addition to quantity surveyors) could be caught under the heading “surveying work” in section 104(2) of the Construction Act 1996 or, for that matter, any other part of section 104. Establishing whether a role comes within the Act can be important to surveyors wanting to exercise their rights under the Act. For example, their rights in relation to payment or suspension, or to employers wanting to pursue professional negligence claims against surveyors via adjudication. Continue reading

REUTERS | Stephen Hird

Last time, I looked at recent developments in mediation, including in light of the new Civil Procedure Rules. This time, I’m looking at the mediation of neighbour disputes.

Neighbour disputes often have two common features: hostility and (if the dispute goes as far as trial) the potential for huge legal costs to be run up. However, in my experience there is another way: mediation.

If I was asked how to persuade one neighbour to suggest mediation to the other, I’d say the answer lies in explaining the potential financial and non-financial benefits of taking any neighbour dispute to mediation. Continue reading

REUTERS | Eduardo Munoz

This post looks at the practical steps in making head office overhead and profit claims, referring to Akenhead J’s blockbuster decision in Walter Lilly v Mackay. Most will know that the court rejected the Scottish (apportionment) approach to concurrent delay and, no doubt, almost all will know of Mr Mackay’s uncompromising approach to his contractor and professional team. However, this article is about neither of those aspects…

…in addition, the case gives useful guidance on what is needed to prove head office overhead and profit claims, which (in short) seems to amount to a lever arch folder, a weekly meeting and a willingness to file. The court also appears to have relaxed the test of “ascertainment” in loss and expense claims.

Continue reading

REUTERS | Bob Strong

There was a good turnout for my talk to the Society of Construction Law on 4 June on retention of title and vesting clauses, despite the counter attraction of one of the first sunny days of summer.

As I said in the talk, this subject is notoriously a legal minefield where minute differences in clause wording are pored over in great detail in the case law and textbooks. However, the subject often arises rather more starkly in the context of insolvency, usually of the main contractor. Indeed, my first experience of this type of clause was against the background of sub-contractors clamouring for their goods back or other recompense, and pointing to the small print of their supply documents. Continue reading

REUTERS | Russell Boyce

Parties too often under-estimate the value of having their case on quantum in order in the lead up to a hearing. In the context of complex high value construction disputes much has been written about the role of experts and ensuring that their evidence is properly presented to the court. The court’s gaze is increasingly turning to liability experts, particularly in the context of delay analysis.

Does this mean that the need to get the figures right and the claim substantiated is just too obvious that we don’t need reminding? After all in the vast majority of the cases we are involved with, the parties are fighting over how much money is owed to whom or the “real” cost of remedying defective work, and they can’t do that without properly presenting their case on quantum, can they? Continue reading

REUTERS | Ina Fassbender

Earlier this year, I raised the possibility of adjudicator-bias in the context of adjudicator’s being paid (or not) following Lord Dyson’s judgment in PC Harrington Contractors Ltd v Systech International Ltd. What I wondered was whether it was arguable (or at least would be argued by some) that being paid at the end of the adjudication process would influence an adjudicator in favour of a particular party when he was making his decision.

While I’m unaware of this proposition being tested by the courts yet, it is possible that we will see the argument in enforcement proceedings in the not-too-distant future. Meanwhile, until then, another case concerning allegations of bias caught my eye recently. This time, it was a judge being asked to recuse himself for bias. Continue reading

REUTERS | Carlos Barria

Delays frequently occur in construction projects. Therefore, many construction contracts make delay, or rather a failure to proceed regularly and diligently, a default event giving rise to the right to terminate. However, what happens when there is no express right and the project falls into serious delay? Does the injured party have a right at common law to treat the delay as a repudiatory breach of contract and terminate?

The Court of Appeal considered this question in Telford Homes (Creekside) Ltd v Ampurius Nu Homes Holdings Ltd. Continue reading

REUTERS | Jumana ElHeloueh

I’ve blogged before about the advantages that adjudication and arbitration can sometimes offer over the court system. For example, last year I considered this topic after West Country Renovations v Mr and Mrs McDowell, where Akenhead J decided that claims for less than £250,000 should be commenced in county courts or other High Court centres outside London that have designated TCC judges.

I’ve recently completed an adjudication where the parties decided to use it as a means of finally deciding their dispute. Continue reading

Share this post on: